Item
|
Materials
|
Labor
|
Subcontracted
|
Total
|
Sheetrock and tape 3 floors
|
|
|
$16,000.00
|
$16,000.00
|
Hardwood floor - 3100 sq ft.
|
|
|
$16,000.00
|
$16,000.00
|
Kitchen / 3 ea.
|
|
|
$21,000.00
|
$21,000.00
|
Heating / 3 furnaces forced hot air
|
|
|
$15,000.00
|
$15,000.00
|
Plumbing w/fixtures
|
|
|
$15,000.00
|
$15,000.00
|
Electric
|
|
|
$10,000.00
|
$10,000.00
|
Trim
|
$6,000.00
|
$6,000.00
|
|
$12,000.00
|
Interior doors 15 ea.
|
$1,500.00
|
$1,500.00
|
|
$3,000.00
|
Demo
|
$2,800.00
|
$7,000.00
|
|
$9,800.00
|
Vinyl
|
$6,000.00
|
$12,000.00
|
|
$18,000.00
|
Windows 21 ea.
|
$7,350.00
|
$5,000.00
|
|
$12,350.00
|
Interior painting
|
|
|
$13,000.00
|
$13,000.00
|
Exterior painting
|
|
|
$6,000.00
|
$6,000.00
|
Exterior doors 8 ea.
|
$8,000.00
|
$4,000.00
|
|
$12,000.00
|
Asbestos abatement
|
|
|
$10,000.00
|
$10,000.00
|
Miscellaneous framing
|
$5,000.00
|
$6,000.00
|
|
$11,000.00
|
Insulation
|
$4,700.00
|
$4,000.00
|
|
$8,700.00
|
Permit and plans
|
|
$1,500.00
|
$5,000.00
|
$6,500.00
|
Additional parking
|
$2,000.00
|
$2,000.00
|
|
$4,000.00
|
Fire stop and strapping
|
$2,000.00
|
$2,000.00
|
|
$4,000.00
|
Total cost
|
$45,350.00
|
$41,500.00
|
$127,000.00
|
$223,350.00
|
|
|
Price Includes
Sheetrocking costs will include: all sheetrocking necessary for three apartments and labor to hang and tape including fire-rated sheetrock in all hallways, basement and first and second floor ceilings. Hardwood floor costs will include: 3,100 square feet of oak hardwood flooring, materials, installation and finishing with three coats of clear polyurethane. Kitchen costs will include: refrigerators, stoves, cabinets and counters for three separate kitchens. Heating costs will include: 3 furnaces, forced hot air and 3 thermostat zones. Plumbing costs will include: three finished full baths with all fixtures (3-piece tub, vanity and toilet) and three half baths (vanity and toilet), three kitchen sinks.
Heating costs will include: 3 furnaces, forced hot air and 3 thermostat zones. Electrical costs will include: outlets and switches, all lighting fixtures, one 3-panel meter box and three breaker boxes, one electric washer and dryer hook-up in basement. Trim costs will include: all standard baseboard and standard casing. Interior door costs will include: an allowance of $100/door for 15 new interior hollow core molded colonial doors and the necessary labor to install. Demo costs will include: removal of any waste materials from the interior of the house, removal of existing siding and windows, along with dumpster fees and removal from property. Vinyl costs will include: installing standard vinyl siding to the exterior of the house (approx. 40 squares). Window costs will include: an allowance of $350/window for 21 new vinyl windows and the necessary labor to install. Interior painting costs will include: costs and labor to coat all three apartments with primer and one color all walls, one color for ceiling and one color for all trim. Exterior painting costs will include: sand down/restore decorative wood on front porch and gable rake edges. Exterior/fire-rated door costs will include: an allowance for $1000/door including the labor for front and back door of building and hallway doors to each apartment. Asbestos abatement costs will include: cost to remove and dispose of hazardous materials on the exteriors of the building by a state-licensed disposal company. Miscellaneous framing costs will include: retrofit to install new windows and doors, adjustments to the floorplan and install an additional means of an egress stairwell to the third floor. Insulation costs will include: purchase and install insulating materials needed to meet the R-value required by the city of New Haven. Permit and plan costs will include: drawing up plans to pass zoning, building and fire marshall requirements and the cost to obtain the building permit. Additional parking costs will include: the city of New Haven requires a three-family home to have additional parking - this will include the cost and labor involved and installing additional parking spots in the back yard. Fire stop and strapping costs will include: the city of New Haven requires balloon-framed structures to have additional fire blocking and wind-resistant strapping. This will include the labor and materials to bring the home up to required code.
|
|